15. During the planning phase for the expansion of a services company, stakeholders conducted a feasibility study to establish the type of new service the company should provide. During an alternatives analysis, another type of service was determined to be more effective. The change control board (CCB) has approved the change request for the alternative service. What should the project manager do?