Test your knowledge on PMP principles, take a mini exam!

Free PMP Practice Exams, Mini Exam 3:

15 Questions of mixed domains.

1. After completing stakeholder analysis the project manager enters action planning. What should be done for stakeholders with no interest or influence?

 
 
 
 

2. A project manager is leading a project with seven key stakeholders. What is the most important aspect of stakeholder management?

 
 
 
 

3. A team postpones user testing due to a weak server and orders a new one. What should the project manager do moving forward?

 
 
 
 

4. A project sponsor requests early resource estimates before the project management plan submission. What should the project manager do?

 
 
 
 

5. During iteration planning the team finds that some high-value user stories have significant risks. What should the agile project manager do?

 
 
 
 

6. A project begins but stakeholders are declining meetings and expressing complaints. What should the project manager have done to avoid this?

 
 
 
 

7. A company undergoing business transformation assigns a project manager to a new business line initiative. What should the team do before defining scope?

 
 
 
 

8. After 20 percent of a project is completed the customer switches data center providers. The new provider requests a meeting to discuss impacts if requirements are not properly gathered. Which project areas would be affected?

 
 
 
 
 

9. A project manager preparing a third progress report identifies delays due to late material deliveries. The first two reports showed the project was on track. What should be done next?

 
 
 
 

10. A customer requests a change in functionality for the next iteration but the assigned specialist has been reassigned to another project. What should the project manager do first?

 
 
 
 

11. A research and development department is launching a new business line. What should the project manager do to improve project success?

 
 
 
 

12. A company outsources a project using a fixed-price contract. During execution the supplier agrees to additional customer requirements not in the contract. To stay on schedule both parties add more resources. What technique is being applied?

 
 
 
 

13. A product owner consistently asks about budget spent per iteration instead of product details. What should the project manager have done earlier?

 
 
 
 

14. A project manager schedules status meetings and standups during project setup but business stakeholders decline the meetings. What should the project manager do?

 
 
 
 

15. A project manager is forming a large team for a complex project and wants effective communication. What should the manager do?

 
 
 
 

Scroll to Top