Free PMP Practice Exams, Basic Test 1: Test Your Knowledge on these free basic PMP principles before going to harder topics 1. A project team decides to buy insurance against potential hurricane damage. What risk response strategy is this? Avoidance Mitigate Transfer Acceptance 2. What’s the next step after defining project activities? Sequence Activities Develop Schedule Define Scope Create WBS 3. The project team has been brought together for the first time to work on a network upgrade project. They were able to learn about the functions they will doing on the project and what their roles will be. What will the team do next, according to Tuckman’s ladder? Forming Storming Norming Performing 4. A vendor announces a two-week delay in server delivery. Which project document should be updated immediately? Change request Project schedule Issue log Work breakdown structure 5. What is a user story? A story about the end-user so the team understands the feature completely. A piece of functionality small enough to be completed in one to three days A description of the feature from the viewpoint of the customer. A prioritized backlog that the team can choose features from. 6. Stakeholders access project status reports online at their convenience. What type of communication is this? Interactive communication Technical communication Pull communication Push communication 7. A team completes a deliverable. What’s the project manager’s next step? Check the deliverable for quality requirements Close the project Ask the team to review the deliverable Get acceptance from the project sponsor 8. In which process does the project manager define the stakeholder engagement approach? Identify stakeholders Plan communications Plan stakeholders engagement Manage stakeholders engagements 9. A project team’s brainstorming ideas are not organized. What tool can help visually organize them? Matrix diagram Flowchart Pareto diagram Mind mapping 10. Team members display disrespectful behavior, causing conflict. What’s the project manager’s best action? Stop the project Release the team Inform the sponsor Implement ground rules Loading …