Test your knowledge on PMP principles, take an Agile exam!

Free PMP Practice Exams, Agile Exam 1

1. A project manager is new to the organization and is assigned to replace the project manager of an active project. What should be one of the first things the project manager does?

 
 
 
 

2. A project manager is part of a project that has a scrum team. The team members are unfamiliar with the distinction between risks and issues and prefer to use the concept of impediments. For which of the following would the team be unable to apply the concept of impediments?

 
 
 
 

3. A project manager in a project management office (PMO) is tasked with implementing an agile framework. The leadership team expects a seamless transition to agile practices. However, the project team has no experience with agile projects. The project manager recognizes that the team will face challenges in this transformation. Which three factors should the project manager prioritize to ensure a successful transition to agile practices?

 
 
 
 
 

4. A project manager is assigned a project for a customer with a history of being demanding and unclear about requirements. The customer has refused to accept previous deliverables without providing clear feedback. How should the project manager proceed with this project?

 
 
 
 

5. Which of the following steps should an Agile project manager of a newly formed virtual team take to help the organization succeed?

 
 
 
 

6. A project manager is running an agile project that is half completed. During the most recent sprint retrospective, the team members see that they worked more hours than were originally scheduled. How should the project manager address this situation?

 
 
 
 

7. Which agile project parameter is least likely to change during project execution?

 
 
 
 

8. An agile team finds it difficult to complete a checklist because they have different interpretations of what the project aims to achieve. How can the project manager help them gain a common understanding of the project’s overall purpose?

 
 
 
 

9. In a scaled agile framework, which responsibilities of a release train engineer can be performed by a project manager? (Choose 3).

 
 
 
 
 

10. A software developer who is working on a critical component has to take emergency leave from the project. Due to time constraints, the project manager cannot hire a new replacement developer for the team. What should the project manager do to manage the situation?

 
 
 
 

11. During an iteration the team realizes that the project will overrun the budget. This is due to the support resources being involved for longer than planned. Company policy requires immediate notification when there is any change to the budget. What should project manager do to manage the project budget?

 
 
 
 

12. A project manager is leading a daily standup meeting when a team member requests that other team members take on some of their assigned work because they are feeling overwhelmed with an upcoming deadline. What should the project manager do next?

 
 
 
 

13. During a daily standup, a stakeholder unexpectedly joins the meeting and criticizes the performance of one of the team members. After this, the team member is very distracted from their work and their productivity noticeably decreases. What should the team member do in this scenario?

 
 
 
 

14. A team member informs the project manager during a project meeting that a due task was not completed on time because of a last-minute work crisis. What should the project manager do?

 
 
 
 

15. A project that should have been 90% complete by now is only 50% complete. The total project budget is $100,000 and the actual cost of work performed is $60,000.

What can be determined from this information?

 
 
 
 

Scroll to Top