Test your knowledge on PMP principles, take an Agile exam!

Free PMP Practice Exams, Agile Exam 2

1. A project manager has been assigned to a big project. The project sponsor would like the project manager to perform a stakeholder analysis.

Which points should the project manager consider while performing this analysis?

 
 
 
 

2. During the fourth iteration of an agile project, the customer requests a technical change to the development of the project deliverable.

What should the project manager do in this situation?

 
 
 
 

3. A project management organization needs to assess the performance of two project teams. Both projects have the same scope of work, but Team 1 works virtually and has calculated 100 story points, while Team 2 works in the office and has calculated 80 story points. Which team has the better performance?

 
 
 
 

4. After years in a predictive project management environment, the organization has decided to implement agile project management and trains the project manager on this approach. The team begins their next project using agile, but after five sprints the team still is dependent on the project manager to make decisions related to the project. How can the project manager help the team?

 
 
 
 

5. An agile project team has implemented design changes over several iterations. The data privacy officer is concerned because their team wasn’t involved in these decisions. How should the project manager address these concerns?

 
 
 
 

6. A project manager has started a new project with a 24-month timeline. Soon after the kickoff, the sponsor informs the project manager that the timeline needs to be shortened to 6 months. What should the project manager do in this scenario?

 
 
 
 

7. A project team has an after-hours get-together. One of the team members who was recently hired and new to the team did not receive an invitation to the get-together. At the next few standups, the new employee is visibly upset and does not participate much during the sessions.

How should the project manager address this situation?

 
 
 
 

8. The director of security compliance is upset because the compliance team has not been informed about the product design decisions taken by the agile team members over the past five iterations. What should the project manager do to start correcting the situation?

 
 
 
 

9. The product owner wants to launch a product even though it lacks some features identified in the MVP. A stakeholder is not satisfied with this version and feels it needs to meet the previously agreed-upon MVP definition. How should the project manager proceed?

 
 
 
 

10. Just before a project meeting, a team member informs the project manager that a critical task was not completed on time.

What should the project manager do?

 
 
 
 

11. After a few sprints have been completed on a global project, the quality assurance team, based in a different country from the PM, has generated a long defect list. The PM is certain that these issues are not related to project quality, but are from language misinterpretation. What should the project manager do to address these issues

 
 
 
 

12. An Agile team is regularly missing milestones and are unable to meet the pace of the sprints. How should the project manager proceed?

 
 
 
 

13. After the project manager just completed the scope definition for the product’s next version release and communicated the scope statement to all stakeholders, a key stakeholder has submitted several requests for new functions.

What should the project manager do next?

 
 
 
 

14. At the end of an iteration, a team member tells the project manager that a planned task is unfinished because of an issue that appeared days ago but could not be resolved. Why should the project manager discuss the issue during the retrospective to prevent this type of situation in the future?

 
 
 
 

15. The stakeholders and project team working on an agile project meet with the project manager at the end of an iteration. The project manager learns that the schedule is slipping, although all work was planned to meet the high-level objectives outlined in the project scope.

What should the project manager have done to keep the project on track?

 
 
 
 

Scroll to Top