1. An organization has implemented agile for its recent projects, but all of the recent agile projects have missed their delivery milestones. The sponsors for the agile projects are regularly adding new requests to the projects. A project manager is given a new agile project and finds that it has a vague project objective and no clear definition of done (DoD). What should the project manager do?

 
 
 
 

2. A project manager typically conducts retrospective sessions at the end of a project. However, the sponsor believes that retrospectives are a waste of time and budget, and instructs the project manager to significantly reduce or eliminate retrospectives in future projects.

What potential outcome could arise from the sponsor’s directive?

 
 
 
 

3. A project manager secures project approval with a constrained budget due to fiscal limitations. The sponsor emphasizes no additional funds are available during the current fiscal year. The product owner is concerned that the tight budget will impact the project.

What should the project manager prioritize?

 
 
 
 

4. During a standup, a project team member suggests modifying some features to benefit from a new opportunity. Another team member expresses concern regarding the user experience resulting from the proposed feature.

How should the project manager address this situation?

 
 
 
 
 

5. During a team meeting, team members were discussing the external dependencies of a project and asked the project manager for advice. What should the project manager ask the team to do?

 
 
 
 

6. During the kick-off meeting an important agile project, the project manager sets the policies and procedures to be followed throughout the project. Midway through the project, the project manager finds that some of the project team are failing to follow the established procedures.

What should the project manager do in this scenario?

 
 
 
 

7. In a new agile project, the team is using Kanban Method. Kanban board acts as an information radiator to anyone who sees it, providing up-to-date information on the status of the work of the team.

How is the Kanban board technology considered?

 
 
 
 

8. A PMO is moving from waterfall to agile project management. The project team has been trained on agile but encounter issues working with company executives using the new processes.

How should project manager address this issue?

 
 
 
 

9. Two agile teams are collaborating on a project. Team A’s output is not complete enough for Team B to integrate into their backlog.

According to servant leadership and agile principles, how will the project manager resolve this situation?

 
 
 
 

10. A key stakeholder is leaving a project,  additionally, the current project manager is being moved to a more urgent project and is instructed to hand off project management duties to a new project manager.
What step should the current project manager take next?

 
 
 
 

11. A project manager receives an email from a customer detailing reservations about the project deliverables. How should the project manager address the customer’s reservations?

 
 
 
 

12. Which is a key factor that servant leadership aims to establish in order to improve team performance?

 
 
 
 

13. A project manager is leading a development project for a high-profile client with strict deadlines. During a sprint, the project manager notices that the team is struggling to complete user stories as planned due to unforeseen technical complexities.

What is the most appropriate action to take?

 
 
 
 

14. A project manager is struggling to keep a technical system implementation on track after the loss of a key team member two months ago. The project has missed multiple milestones and is now in critical status.

What should the project manager have done to prevent this situation?

 
 
 
 

15. A project manager is asked to provide the remaining time planned for the project. What tool should the project manager use to provide this information?

 
 
 
 