Free PMP Practice Exams, Basic Test 2:

Test Your Knowledge on these free basic PMP principles before going to harder topics

1. During project execution, a key stakeholder requests a costly change.

What’s the next step after assessing the change’s impact?

 
 
 
 

2. When selecting user stories for the next iteration, what’s the most important factor for the development team to consider?

 
 
 
 

3. A project manager provides a high-level estimate based on a similar project encountered in the past.

Which estimation technique is this?

 
 
 
 

4. An activity on the critical path has a duration of 3 days.

What’s the slack time for this activity?

 
 
 
 

5. Two team members are unable to agree on the order of project tasks, so they postpone the decision to a later date.

Which conflict resolution technique is used?

 
 
 
 

6. How are changes handled on an Agile project?

 
 
 
 

7. A sponsor constantly requests updates and meetings, disrupting project progress.

What management style is this?

 
 
 
 

8. Increased costs are incurred for employee training and equipment to meet quality requirements.

What describes this cost?

 
 
 
 

9. A programmer decides to bill the customer based on how many lines of code are in the final application.

Which estimating technique is this?

 
 
 
 

10. Additional cost is added to the project budget due to known risks.

What is this cost called?

 
 
 
 

Scroll to Top