Free PMP Practice Exams, Basic Test 3: Test Your Knowledge on these free basic PMP principles before going to harder topics 1. A project manager adds resources to finish a project earlier. What schedule compression technique is being used? Critical path method Crashing Schedule variance Fast tracking 2. There are disputes with a contractor regarding completed work. What should the project manager do first? Meet with the contractor to understand why there are conflicts Contact claims administration Review the contract Meet with the project team members to understand their project concerns 3. A project team discovers a faster server installation method. Where should this information be documented? Lessons learned register Opportunity register Risk register Knowledge management register 4. What’s the primary benefit of Agile over traditional project management? Agile delivers value incrementally Agile project requires funding up front Traditional delivers values all up front Traditional delivers value at the beginning 5. A project manager wants to compare project performance against industry best practices. What tool is most relevant? Benchmarking Plan quality management Meetings Collect requirements 6. Money already spent on a project is called? Project budget Spent cost Opportunity cost Sunk cost 7. What is the project manager’s ideal role in conflict resolution? Facilitator Director Dictator Advisor 8. What document shows the availability of project resources? Project team calendar Resource calendar Lessons learned register Availability calendar 9. A project manager resolves team conflicts. What process is being performed? Acquire Team Control Resources Manage Team Control Scope 10. A prototype smartphone has defects. What tool can help identify the root causes? Ishikawa diagram Assumptions analysis Histograms Inspections Loading …