Free PMP Practice Exams, Basic Test 5:

Test Your Knowledge on these free basic PMP principles before going to harder topics

1. Frequent scope changes during project execution often indicate what underlying problem?

 
 
 
 

2. Contractor payments are made according to the contract terms.

Which process does this describe?

 
 
 
 

3. Which is NOT a principle of Agile planning?

 
 
 
 

4. What is the most important concept in quality management?

 
 
 
 

5. A project manager can start some project work before predecessor tasks are finished to shorten the project duration.

What technique is being used?

 
 
 
 

6. HR accepts the overtime requests in order to finish the project earlier.

What schedule compression technique is being used?

 
 
 
 

7. A project status report shows a CPI of 1.1 and an SPI of 1.14.

What does this indicate?

 
 
 
 

8. Planning is done at multiple points in time on an Agile project as more information becomes available.

What is this called?

 
 
 
 

9. What should be added to the schedule to account for a mandatory delay between activities?

 
 
 
 

10. A project team completes and tests a server deployment according to requirements.

Which process group have they completed?

 
 
 
 

Scroll to Top