Free PMP Practice Exams, Basic Test 5:

Test Your Knowledge on these free basic PMP principles before going to harder topics

1. HR accepts the overtime requests in order to finish the project earlier.

What schedule compression technique is being used?

 
 
 
 

2. Which is NOT a principle of Agile planning?

 
 
 
 

3. A project status report shows a CPI of 1.1 and an SPI of 1.14.

What does this indicate?

 
 
 
 

4. Planning is done at multiple points in time on an Agile project as more information becomes available.

What is this called?

 
 
 
 

5. A project manager can start some project work before predecessor tasks are finished to shorten the project duration.

What technique is being used?

 
 
 
 

6. Frequent scope changes during project execution often indicate what underlying problem?

 
 
 
 

7. Contractor payments are made according to the contract terms.

Which process does this describe?

 
 
 
 

8. A project team completes and tests a server deployment according to requirements.

Which process group have they completed?

 
 
 
 

9. What should be added to the schedule to account for a mandatory delay between activities?

 
 
 
 

10. What is the most important concept in quality management?

 
 
 
 

Scroll to Top