Free PMP Practice Exams, Hybrid Exam 2

Test your knowledge on PMP principles, take a Hybrid Methodology exam!

Free PMP Practice Exams, Hybrid Exam 2:

1. A contingency plan introduces a new risk that customer interactions may slow down, what type of risk is this?

 
 
 
 

2. A company is bidding and there is a penalty clause for delay, what should the project manager do?

 
 
 
 

3. The team is deciding how to start risk management, what is the first step?

 
 
 
 

4. While developing the initial schedule baseline, two resources for a critical task are reassigned to another strategic project.

What should the project manager do?

 
 
 
 

5. A risk identification workshop is needed for a team in six countries, which technique is most appropriate?

 
 
 
 

6. A new project has strict time and budget constraints and similar projects failed due to scope creep, what should the project manager do now?

 
 
 
 

7. A diverse team is struggling to work together, how does meeting to develop mutual values and a shared vision facilitate better teamwork?

 
 
 
 

8. To analyze similar issues across portfolio projects which artifact should be used first?

 
 
 
 

9. A complex multi site manufacturing project enters a high activity phase, what should be done first to keep stakeholders informed?

 
 
 
 

10. A problem that may impact objectives has occurred, where should it be recorded and monitored?

 
 
 
 

11. During risk planning, which risks should be assessed and categorized?

 
 
 
 

12. There is limited historical data and uncertainty is high, what should the project manager do?

 
 
 
 

13. What leadership characteristic must a project manager demonstrate when reporting realities to stakeholders?

 
 
 
 

14. A laptop with proprietary data is lost during travel, what should the project manager do?

 
 
 
 

15. During a status meeting, stakeholder expectations are misaligned and unmet.

What should the project manager do to keep the project moving?

 
 
 
 

Scroll to Top