Free PMP Practice Exams, Hybrid Exam 2

Test your knowledge on PMP principles, take a Hybrid Methodology exam!

Free PMP Practice Exams, Hybrid Exam 2:

1. To analyze similar issues across portfolio projects which artifact should be used first?

 
 
 
 

2. There is limited historical data and uncertainty is high, what should the project manager do?

 
 
 
 

3. A problem that may impact objectives has occurred, where should it be recorded and monitored?

 
 
 
 

4. What leadership characteristic must a project manager demonstrate when reporting realities to stakeholders?

 
 
 
 

5. The team is deciding how to start risk management, what is the first step?

 
 
 
 

6. A contingency plan introduces a new risk that customer interactions may slow down, what type of risk is this?

 
 
 
 

7. A risk identification workshop is needed for a team in six countries, which technique is most appropriate?

 
 
 
 

8. A diverse team is struggling to work together, how does meeting to develop mutual values and a shared vision facilitate better teamwork?

 
 
 
 

9. A company is bidding and there is a penalty clause for delay, what should the project manager do?

 
 
 
 

10. During risk planning, which risks should be assessed and categorized?

 
 
 
 

11. A laptop with proprietary data is lost during travel, what should the project manager do?

 
 
 
 

12. A new project has strict time and budget constraints and similar projects failed due to scope creep, what should the project manager do now?

 
 
 
 

13. A complex multi site manufacturing project enters a high activity phase, what should be done first to keep stakeholders informed?

 
 
 
 

14. While developing the initial schedule baseline, two resources for a critical task are reassigned to another strategic project.

What should the project manager do?

 
 
 
 

15. During a status meeting, stakeholder expectations are misaligned and unmet.

What should the project manager do to keep the project moving?

 
 
 
 

Scroll to Top