Test your knowledge on PMP principles, take a mini exam!

Free PMP Practice Exams, Mini Exam 1:

1. Who has the authority to act as a key stakeholder and decision-maker throughout a project’s lifecycle to ensure business alignment?

 
 
 
 

2. A project requires imported components; but the exchange rate may lead to a loss. The project manager decides not to act. What risk response was applied?

 
 
 
 

3. A project manager invites stakeholders to daily standup meetings; but none attend. What should be done?

 
 
 
 

4. A project manager identifies new risks that might impact critical tasks and needs to report them. Besides the risk report; which document should be referenced?

 
 
 
 

5. During iteration planning; some user stories with high value are also high risk. What should the project manager do?

 
 
 
 

6. A project team is frequently missing milestones; and a stakeholder is concerned. The project manager also identifies team conflict and missing skills. What should be done?

 
 
 
 

7. A project team is waiting for a new server for end-user testing; but the delay is affecting the schedule. What should the project manager do?

 
 
 
 

8. A market regulation change may impact a project nearing completion. What should the project manager do?

 
 
 
 

9. A project is selected for a compliance audit; but the customer believes it is unnecessary and asks the team to avoid disruption. What should the project manager do?

 
 
 
 

10. A project manager struggles to manage stakeholders due to unclear engagement levels. What should be done?

 
 
 
 

11. A multinational company is implementing software that will impact multiple departments. What should be developed to align stakeholder expectations with the final product?

 
 
 
 

12. A project manager leading an agile project wants to enhance team motivation. What should be done?

 
 
 
 

13. A functional manager removes a technical specialist from a project to handle a critical customer issue; delaying a milestone. What should the project manager do first?

 
 
 
 

14. A project’s steering committee is replaced by a single sponsor due to budget cuts. What should the project manager do?

 
 
 
 

15. A project team is learning agile methods but is losing motivation during daily standups. What could be done in this scenario?

 
 
 
 

Scroll to Top