Test your knowledge on PMP principles, take a mini exam!

Free PMP Practice Exams, Mini Exam 2:

1. A company is launching a major production overhaul project. Given its high-risk nature; executives emphasize its critical success. What should the project manager prioritize first?

 
 
 
 

2. An agile project includes 100 user stories across ten iterations; each worth $100. After five iterations; 50 user stories are completed; actual spending is $4500. What is the status?

 
 
 
 

3. A multinational project’s sponsors have implemented an automated reporting system at the end of each phase to unify efforts. They intend to apply this model to future projects. What should the project manager do?

 
 
 
 

4. A hospital CEO requests a 30% reduction in implementation time for a project involving three MRI units. Who should the project manager consult for realistic adjustments?

 
 
 
 

5. A project is completed with all deliverables meeting requirements; but testing revealed a high number of errors. What should the project manager have done earlier?

 
 
 
 

6. A government regulation change affects a project already in execution. The law takes effect soon and will impact the budget and schedule. What should the project manager do?

 
 
 
 

7. A key stakeholder in an agile project was engaged initially but became less involved after receiving a promotion. Later; they rejected a deliverable; leading to major rework. What should the project manager have done to prevent this?

 
 
 
 

8. A project team developing credit card software discovers during testing that foreign cards are not accepted; making the system nearly unusable. What should have been done to prevent this?

 
 
 
 

9. A project manager joins an organization and is assigned a project with a vague scope and unclear deliverables. How should the project manager proceed?

 
 
 
 

10. Stakeholders express dissatisfaction with a project deliverable. What should the project manager do next?

 
 
 
 

11. A complex project across four countries is near completion. Functional managers are preparing closeout documents. Why should the sponsor sign off on deliverables?

 
 
 
 

12. A project manager leads a software development project that is significantly behind schedule. Despite motivation efforts; the team has not improved. What should be done first?

 
 
 
 

13. A project manager joins an ongoing industrial project. The latest performance indices show CPI=0.42 and SPI=0.20. What does this indicate?

 
 
 
 

14. During a team meeting; the project manager notices a conflict among three key team members with different personalities. What should be done first?

 
 
 
 

15. A high-risk project has faced multiple realized risks; however; despite implementing responses; issues persist. What should the project manager do to identify weaknesses in the risk management process?

 
 
 
 

Scroll to Top