Test your knowledge on PMP principles, take a Waterfall (Predictive) exam!

Free PMP Practice Exams, Waterfall Exam 1:

1. A  functional manager leaves the company and is no longer involved in the current project.

What should the project manager do first?

 
 
 
 

2. Throughout the project, the project manager takes coffee breaks with the team and asks if they have ideas on how to improve their way of working.

The project manager’s approach is in line with which theory?

 
 
 
 

3. A customer identifies performance issues on a newly developed product.

Why should the project manager estimate the Cost of Quality (COQ) for this project?

 
 
 
 

4. New team members joined a project which was already in the execution phase.

Which document should the project manager update first?

 
 
 
 

5. As a predictive project enters the execution phase, a functional manager discovers that one of the materials to be used in the product will have a negative effect on the environment and urges the project manager to switch to a more environmentally friendly material.

What should the project manager’s initial response be?

 
 
 
 

6. After comparing actual results to the performance measurement baseline, the project manager discovers that the project’s work and cost performance measures are better than expected. The project manager doubts that these positive variances can continue until the end of the project.

What should the project manager do?

 
 
 
 

7. During a status meeting of a manufacturing project in its implementation phase, a team member tells the project manager that a solution has been found for a persistent failure on equipment used in the implementation. However, this solution is temporary, and the equipment could fail again in the future.

Which document should the project manager update?

 
 
 
 

8. Midway through the project, one stakeholder leaves the company.

Which document should the project manager update?

 
 
 
 

9. A project manager is preparing the project management plan and notices that there is a limited amount of detailed information about the activities, however the project manager worked on a similar project in the past.

What should the project manager do to calculate the expected duration of the project.

 
 
 
 

10. The project manager sees that the team is causing delays resulting in a negative schedule variance.

What should the project manager do?

 
 
 
 

11. The project deliverables were refused by the customer.

What should the project manager do to gain approval?

 
 
 
 

12. A project manager is committed to the success of a multinational project with tight deadlines. A new team member is continually late or misses status meetings. In a one-on-one with the project manager, the team member expresses the belief that working on deliverables is more important than attending status meetings.

What should the project manager do?

 
 
 
 

13. A new project manager had been assigned by the project sponsor to new critical project with tight budget and time constraints.

What should the project manager do first?

 
 
 
 

14. During the planning stage of a complex project, the sponsor identifies a need for a specialist who is a citizen of a foreign country. The budget does not allow for this specialist’s travel expenses.

What should the project manager do?

 
 
 
 

15. In a large construction project, a fuel price increase was identified as a risk during the planning stages. The identified risk was assigned high probability with low impact. The price increase would not be more than 2%. However when the project begins, a 20% fuel price increase goes into effect.
What should the project manager do?

 
 
 
 

Scroll to Top