Test your knowledge on PMP principles, take a Waterfall (Predictive) exam!

Free PMP Practice Exams, Waterfall Exam 2:

1. A project team is using a Waterfall methodology to develop a new software application. During the requirements gathering phase, a key stakeholder requests a significant change to the core functionality. This change would require substantial rework in the design and development phases.

What should be the first action for the project manager?

 
 
 
 

2. A supplier reports that they are over capacity, which may delay their delivery.

Which document should the project manager update first?

 
 
 
 

3. A project manager who comes from a directive behavioral orientation, wants to build a high-performing team that is motivated and productive, the team will be working on a complex project with a tight deadline.

How should the project manager lead this team?

 
 
 
 

4. After weeks of dealing with conflicts, compromising, and achieving the project goal, team members are focusing on documenting the lessons learned to be shared with stakeholders, sponsors, and future project teams.

In which Tuckman ladder stage are they?

 
 
 
 

5. The project manager is facing difficulties persuading stakeholders to adopt new technologies in the project.

What should the project manager have done to avoid this resistance?

 
 
 
 

6. A project team often asks questions about the rationale for their work and how the client perceives their progress and deliverables.

What should the project manager do to build trust and get the team engaged?

 
 
 
 

7. A large risk to a project is identified, and the risk management plan is executed.

What should the project manager do next?

 
 
 
 

8. The team is offered 2 days of vacation if they deliver the project on time.

What theory is being applied?

 
 
 
 

9. The supplier of electronic devices has indicated a high likelihood of schedule delays. In response, the project manager, with stakeholder approval, implemented a contingency plan to use temporary rented devices from another source until they receive the original shipment. However, there’s a residual risk that the temporary rented devices might also be delayed, which will impact the project’s regulatory timeline.

What type of risk is the project manager currently facing?

 
 
 
 

10. The project manager recognizes that there is an opportunity to complete the project ahead of schedule after a vendor announces that the equipment can be delivered earlier than anticipated.

What should the project manager do next?

 
 
 
 

11. Which of the following combination of approaches should a team lead take to have a highly motivated and high-performing project team?

 
 
 
 

12. Which is the process that the project manager performs to prioritize individual project risks for further analysis or action by assessing their probability of occurrence and impact, as well as other characteristics?

 
 
 
 

13. Due to increased price volatility, a vendor asks the project manager of a large development project to make a price change that will affect the project contract.

What should the project manager do?

 
 
 
 

14. A project manager has finished the Qualitative Risk Analysis with their team.

Which project documents may require update based on this information?

 
 
 
 

15. The project’s budget was planned using a conservative scenario with high exchange-rate variations, however, the project is highly sensitive to and dependent upon financial market activity. The project manager now wants to review this budget to update the probability and impact of a possible new scenario using current financial conditions.

To what should the project manager refer?

 
 
 
 

Scroll to Top