Free PMP Practice Exams, Waterfall Exam 3

Test your knowledge on PMP principles, take a Waterfall (Predictive) exam!

Free PMP Practice Exams, Waterfall Exam 3:

1. A stakeholder requests more frequent and detailed project status reports than a previous agreement. The stakeholder also expresses interest in getting more involved with the project. How should the project manager address this situation?

 
 
 
 

2. A team for a project is composed of individuals from different backgrounds, ages, and interests. The team is struggling to work together. How would meeting with the team to develop mutual values and a shared vision enable the project manager to facilitate better teamwork?

 
 
 
 

3. While reviewing the quality of deliverables with the team, the project manager determines that several quality issues could have been avoided by using a checklist. The project manager implements a checklist to ensure future deliverables would align with the project management plan. What did the project manager do in this situation?

 
 
 
 

4. A complex manufacturing project has multiple stakeholders in multiple locations. The project is entering a high-activity phase and the project manager needs to ensure that all stakeholders are kept informed with timely updates. What should the project manager do first?

 
 
 
 

5. A functional manager wants to use resources already allocated to a project. What should the project manager of that project do?

 
 
 
 

6. A project manager has been assigned to a newly approved multi-national project. The successful implementation of the project relies on deliverables from a variety of departments. What is the most important thing the project manager can do to ensure the successful implementation of the project?

 
 
 
 

7. A complex project is in the planning phase. The sponsor assigns a newly certified project manager to the project. Upon review of the project charter, the project manager uncovers several factors that could impact the project in unpredictable ways. What should the project manager do?

 
 
 
 

8. During a project status meeting, the project manager discovers that stakeholders have different expectations that are not aligned. None of these expectations have been met, which has created tension in the meeting. What should the project manager do to keep things moving on the project?

 
 
 
 

9. A project is entering the user acceptance testing phase. After several business end users raised questions and concerns, the project manager discovered that critical business requirements were omitted from the business requirements analysis. What should the project manager do to resolve this issue?

 
 
 
 

10. While developing the initial schedule baseline, the project manager learns that a functional manager reassigned two resources needed for a critical task to another strategic project. What should the project manager do?

 
 
 
 

11. A project manager learns that a stakeholder thinks that only certain stakeholders are getting all the project updates and feels left out of the information loop. What should the project manager do?

 
 
 
 

12. A project manager has been assigned to a new project that revisits a previously completed project. Why should the project manager refer to the previous project lessons learned knowledge base and historic information first?

 
 
 
 

13. A project manager identifies a risk during the implementation phase of a project which was not anticipated during planning. How would facilitating a brainstorming session allow the project manager to mitigate the risk while keeping the project on schedule?

 
 
 
 

14. A new project is about to start and is subject to strict time and budget constraints. When reviewing the lessons learned repository, the project manager learns that constant scope creep caused a similar project to fail. What should the project manager do now to avoid project failure?

 
 
 
 

15. During the planning phase for the expansion of a services company, stakeholders conducted a feasibility study to establish the type of new service the company should provide. During an alternatives analysis, another type of service was determined to be more effective. The change control board (CCB) has approved the change request for the alternative service. What should the project manager do?

 
 
 
 